11 - 01 - 2010 Downtown paving work begins Monday in Lewistown
The paving projects start in the west end of town for the next 2 weeks starting today. & motorists are advised of several street closings until this work is done. Some changes in the schedule now have crews paving W. 6th St. from Silversand Ave. to Grove Ave. today. Tomorrow, Grove Ave. from W. 4th St., to W. 6th & all of Franklin Ave. from W. 4th St. to 5th St. will be paved. Pennsylvania Ave. from W. 4th St. to W. 6th St. will be paved on Wednesday. Vehicles need to be removed from these streets by 6am on each day.